GuangDong HuaAo New Alloy Material Co.,Ltd. annual production of 9,000 tons of casting master alloy production line technical transformation and annual production of 20,000 tons of nickel alloy expansion project first announcement


GuangDong HuaAo New Alloy Material Co.,Ltd. annual production of 9,000 tons of casting master alloy production line technical transformation and annual production of 20,000 tons of nickel alloy expansion project first announcement.

 

       According to the "Environmental Impact Assessment Law of the People's Republic of China" and the "Measures for Public Participation in Environmental Impact Assessment" (Order No. 4 of the Ministry of Ecology and Environment) and other relevant regulations, the environmental impact assessment matters related to the "Technical Transformation Project of GuangDong HuaAo New Alloy Material Co.,Ltd. annual production of 9,000 tons of casting master alloy production line" are hereby announced for the first time.

I. Basic Information of the Project

1. Basic Information of Existing and Under Construction Projects

(1) The existing and under construction projects mainly include: Workshop No. 1, Workshop No. 2, Workshop No. 3, Workshop No. 4 finished product warehouse, office building, dormitory building, etc. Workshop No. 1 has built a coreless induction furnace, AOD furnace, horizontal continuous casting equipment, shearing equipment, etc., and completed the environmental protection acceptance on July 21, 2011, with an annual output of 9,000 tons of stainless steel; Workshop No. 2 is constructing a vacuum induction furnace, vacuum mold casting equipment, shot blasting machine, cutting machine, etc., and has not yet undergone environmental protection acceptance, with an expected annual output of 2,000 tons of high-temperature alloy bars; Workshop No. 3 is constructing a vacuum induction furnace, non-vacuum induction furnace, powder spraying equipment, powder screening equipment, etc., and has not yet undergone environmental protection acceptance, with an expected annual output of 300 tons of high-temperature alloy powder; Workshop No. 4 is an under-construction steel slag crushing and sorting workshop, intended to sort the steel slag produced by Workshop No. 1, and has not yet undergone environmental protection acceptance.
(2) Environmental Protection Situation:
Waste Gas: The existing project in Workshop No. 1 has 5 exhaust stacks, which are for coreless induction furnace waste gas, AOD refining furnace waste gas, continuous casting flame cutting waste gas, bar cutting waste gas, and laboratory waste gas, with stack heights of 8 to 17 meters. All have set up environmental protection measures and the discharged waste gas meets the emission standards set by the environmental protection department; Workshop No. 2 is under construction and plans to set up 2 exhaust stacks, with a height of 25 meters, for vacuum smelting waste gas and machining dust, both of which have set up environmental protection measures; Workshop No. 3 is under construction and plans to set up 3 exhaust stacks, with heights of 15 to 25 meters, for vacuum smelting waste gas, non-vacuum smelting waste gas, and atomization classification dust, all of which have set up environmental protection measures; Workshop No. 4 is under construction and plans to set up 1 exhaust stack, with a height of 15 meters, mainly for dust waste gas from steel slag crushing and sorting, which has set up environmental protection measures. Wastewater: This project only generates domestic sewage, which is treated by the self-built sewage treatment station in the factory area to meet the second period Class I standard of Guangdong Province's "Water Pollutant Discharge Limits" (DB44/26-2001) and the quality of urban reclaimed water for urban miscellaneous use (GB/T18920-2002) for greening, toilet flushing, and road cleaning before being partially discharged into the Minzu River, with some reused for greening in the factory area. Noise: Measures such as basic vibration reduction, sound insulation of the workshop, soft connections at the fan inlet and outlet, and installation of silencers are taken to reduce noise; Solid Waste: The factory area has built compliant general industrial solid waste storage places and hazardous waste storage places. The hazardous waste generated has signed disposal agreements with qualified disposal units, and all solid waste is comprehensively utilized or properly disposed of.

2. This technical transformation and expansion project is based on

Project Name: Technical Transformation Project of Guangdong Hua'ao Alloy New Materials Co., Ltd. annual production of 9,000 tons of casting master alloy production line
Project Investment: 20 million yuan
Construction Location: Industrial Zone 2, Hecheng Town, Heshan City
Construction Content and Scale: This technical transformation project will be carried out within the existing factory area, without increasing land area or building area. It plans to add LF furnace, VD furnace, and shearing machine in Workshop No. 1, and add vacuum induction furnace, vacuum continuous casting machine, electric arc furnace, and other equipment in Workshop No. 3, and upgrade the environmental protection measures equipped with the coreless induction furnace and AOD refining furnace for ultra-low emissions. After the technical transformation of Workshop No. 1 is completed, it will enhance the technical level of high-temperature alloys for casting in the factory area, with an annual production of 9,000 tons of casting high-temperature master alloy bars; after the expansion of Workshop No. 3, the annual nickel alloy output of the entire factory will be 20,000 tons.

II. Name and Contact Information of the Construction Unit

Construction Unit: Guangdong Hua'ao Alloy New Materials Co., Ltd. Contact Person: Quan Huifeng Contact Phone: 0750—8383052 Mailing Address: Industrial Zone 2, Hecheng Town, Heshan City III. Name of the Environmental Impact Report Preparation Unit Environmental Assessment Agency: Guangdong Zhihuan Innovation Environmental Technology Co., Ltd. IV. Network Link to the Public Opinion Form See Attachment 1 of this announcement text for details. V. Main Ways for the Public to Raise Opinions Any unit or individual concerned about the construction of this project, and any unit or individual directly or indirectly affected by this project, can send your opinions to the construction unit or the environmental assessment unit in writing, by fax, or by email during the preparation period of the environmental impact report draft. The public is encouraged to provide detailed contact information when expressing opinions so that the construction unit and evaluation unit can promptly provide relevant information back to you.

 

III. Name of the Environmental Impact Report Preparation Unit

Environmental Assessment Agency: Guangdong Zhihuan Innovation Environmental Technology Co., Ltd.

IV. Network Link to the Public Opinion Form

See Attachment 1 of this announcement text for details.

V. Main Ways for the Public to Raise Opinions

Any unit or individual concerned about the construction of this project, and any unit or individual directly or indirectly affected by this project, can send your opinions to the construction unit or the environmental assessment unit in writing, by fax, or by email during the preparation period of the environmental impact report draft. The public is encouraged to provide detailed contact information when expressing opinions so that the construction unit and evaluation unit can promptly provide relevant information back to you.
 

GuangDong HuaAo New Alloy Material Co.,Ltd.
August 26, 2020

Download:

Related News


Environmental Impact Report for the expansion project of GuangDong HuaAo New Alloy Material Co.,Ltd. with an annual production of 2000 tons of high-temperature alloy bars and 300 tons of alloy powder is publicly announced before approval.

Our company has entrusted Guangdong Zhihuan Innovation Environmental Technology Co., Ltd. to undertake the environmental impact assessment work for the "GuangDong HuaAo New Alloy Material Co.,Ltd. annual production expansion project of 2000 tons of high-temperature alloy bars and 300 tons of alloy powder."


GuangDong HuaAo New Alloy Material Co.,Ltd. annual production of 2000 tons of high-temperature alloy rods and 300 tons of alloy powder expansion project environmental impact public participation second announcement

The Environmental Impact Report for the expansion project of GuangDong HuaAo New Alloy Material Co.,Ltd. for an annual production of 2000 tons of high-temperature alloy bars and 300 tons of alloy powder, commissioned by Guangdong Zhihuan Innovation Environmental Technology Co., Ltd.


Public Acceptance Announcement for the Domestic Sewage Treatment Facility of GuangDong HuaAo New Alloy Material Co.,Ltd.

According to the "Decision of the State Council on the <Regulations on the Environmental Protection Management of Construction Project Completion" (State Council Order No. 682), and the Ministry of Environmental Protection's "Announcement on the Release of the <Interim Measures for Environmental Protection Acceptance of Construction Project Completion" (National Environmental Regulation Environmental Assessment [2017] No. 4), the completion environmental protection acceptance situation of the living sewage treatment facilities for the project of Guangdong Huazheng Integrated Metal New Materials Co., Ltd


The first public announcement of the environmental impact assessment public participation information for the GuangDong HuaAo New Alloy Material Co.,Ltd. renovation and expansion project.

GuangDong HuaAo New Alloy Material Co.,Ltd. entrusted Guangdong Zhihuan Innovation Environmental Technology Co., Ltd. to conduct an environmental impact assessment for the technological transformation and expansion project invested and constructed by the company.